Client: P.V. Community Development Corporation
Location: El Paso, Texas
Date of Contract Award: March 23, 2016
Contract Value at Award: 4418 Sunrise: $909,346.86 4420 Sunrise: $817,563.79
Awarded Completion Date: October 1, 2016
Actual Completion Date: In Progress
List of Key Personnel: Project Manager/Site Superintendent/ SSHO
List of major subs/trades: Electrical, Plumbing, HVAC, Abatement, Demolition, Drywall, Carpentry

DESCRIPTION OF PROJECT

4418 Sunrise: This design-bid-build project consists of the complete construction of apartment complexes, including site development and improvements of Building 2 (6,594 sf) comprised of six (6) two (2) bedroom apartments, Building 3 (1,938 sq.) comprised of two (2) two (2) bedroom apartments (1 ADA at ground floor) and Building 4 (2,440 sf) comprised of two (2) three (3) bedroom apartments (1 ADA at ground floor). Total of ten (10) apartments

4420 Sunrise: This design-bid-build project consists of the complete construction of apartment complexes, including site development and improvements of Building 1 (6,594 sf) comprised of six (6) two (2) bedroom apartments, Building 5 (1,938 sq.) comprised of two (2) two (2) bedroom apartments (1 ADA at ground floor) and Building 6 (2,440 sf) comprised of two (2) three (3) bedroom apartments (1 ADA at ground floor). Total of ten (10) apartments.